Wednesday, August 12, 2009

August 12, 2009




We had another great work day today. Thank you, Dave Birney for bringing in your equipment and filling in the low spots in the yard and along the foundation. Over the course of the next few days the yard is going to look a lot different. Tom Hunt helped Jim Cluney put in most of the light fixtures today.

Yesterday Ed Kielenstyne and Jim Cluney finished installing the sewer line in the back yard.

Now guess what! We have the kitchen cabinets, interior doors, and trim all coming in by Friday! This is an absolute miracle since we were not suppose to get them for at least another week. God is so good!

The schedule for work will go like this....

Friday we can use anyone who will be able to help us hang interior doors, put down the base trim, install the kitchen cabinets, and install the shelves in the closets.

We will plan to work Saturday to finish up what we might not get done Friday.

By Tuesday or Wednesday we will have the carpet and vinyl installed.

Counter tops will be here in about a week and then we can finish up the plumbing.

Once the dirt has time to settle we will put in concrete for side walks and step platforms. The steps will then be ready to construct.

We typically work from 8:00 in the morning until 4:30 in the afternoon. If you want to help and can only be there for an hour or two that is great.

Please call ahead and let us know which days you can work so we can figure the number of people we need to feed at lunch time.

Call Jim Cluney at (319) 653-1735

It is amazing how fast things come together when everyone works together to accomplish a common goal. Thanks again....